NOAA Marine Facility construction at Newport Navy Base

NOAA Marine Facility

01

PROJECT SCOPE

Marine Subcontractor – Skanska; Self-performed marine and heavy civil engineering for Skanska; demolition; H-piles; combination bulkhead; trestle; main pier; drilled shafts; underwater tremie concrete; precast panels; fender system; diving; corrosion protection; underwater grouting.

02

CHALLENGES & HIGHLIGHTS

A pile installation issue threatened the schedule. CMCLLC, the general contractor, and the project owner resolved it on-site while maintaining the project’s schedule and budget.

03

OUR RESULTS

Delivered the full marine and heavy civil scope while maintaining schedule and budget, including the new bulkhead, trestle, main pier, floating-dock foundations, fender system, and underwater corrosion-protection work.